By Shore Local News
A powerful Thanksgiving Day nor’easter left approximately 19,000 Atlantic City Electric customers without power as of 1 p.m. Thursday, Nov. 26, as heavy rain, coastal flooding and wind gusts of up to 70 mph battered South Jersey.
Power outage update: 1 p.m. Nov. 26
19,000 customers without power.
14,000 customers have had service restored since the storm began.
Additional outages are expected as severe weather continues across the region. Atlantic City Electric has activated its Emergency Response Organization, deploying all available resources to repair damaged electrical equipment and restore power. Crews will work around the clock throughout the Thanksgiving holiday.
Severe weather complicates restoration efforts
High winds, downed trees, coastal flooding and road closures are creating challenges for utility crews.
Bucket trucks cannot safely operate aerial lifts in sustained winds above 35 mph. Flooding may also prevent crews from accessing damaged electrical equipment.
Estimated restoration times have been temporarily suspended and will be updated once crews can safely assess storm-related damage.
Customers can monitor outages and restoration efforts at atlanticcityelectric.com/storm.
How to report a power outage
Online: atlanticcityelectric.com/storm
Mobile app: atlanticcityelectric.com/MobileApp
Text: Text OUT to 20661. Customers must first text ADD OUTAGE to 20661 to enroll.
Phone: 800-833-7476
Important safety reminders
Never approach or touch downed power lines, even if they appear inactive. Always assume fallen wires and damaged electrical equipment are energized.
Customers should also avoid entering flooded basements or approaching electrical equipment surrounded by water because the water could be energized.
Report downed wires immediately: 800-833-7476.
Additional updates are available through Atlantic City Electric’s Facebook and X accounts.
Atlantic City Electric acknowledged the difficulties of losing power during the Thanksgiving holiday and thanked customers for their patience as crews work to restore service as safely and quickly as possible.